How does the Finish No Earlier Than (FNET) constraint affect my project schedule?

Project Central uses constraint type rules, along with work durations and dependencies, to determine the scheduled start and scheduled end dates of work items in your plan. With FNET selected as the constraint type, the Scheduled End date will be the later of the date entered or the end based on any dependencies. The Scheduled Start date will be the later of calculated end - duration or the start based on any dependencies. This article describes how the FNET constraint works.

1. FNET Constraint Without Dependencies

2. FNET Constraint With Dependencies