How do I reactivate a gate?

Users with the Re-Activate Gate permission for a gated project can reactivate a gate that has already been approved. PowerSteering clears the approval history for the affected gate(s) and changes the status back to "On Track". This article describes how to reactivate a gate.

1. Click Project

Click Project
  • On the Icon Bar, click the Project button.

 Note: Clicking the Project button on the Icon Bar will take you directly to the Summary page of the last work you visited.

2. Select Gate

  • On the status bar, click the blue link for the gate you want to reactivate.

3. Reactivate Gate

Reactivate Gate
  1. Enter a reason for the gate reactivation (optional).
  2. Click Reactivate.

4. View Active Gate

  • The Acceptance gate is now the active gate and approval has been cleared.