How do I capture a baseline in Project Central?

Within Project Central, you have the ability to take a new baseline for an item. This action will overwrite any previous baselines that have been taken for that line item. This article describes how to capture a baseline.

Click here to view a brief video tutorial about setting a baseline.

1. Click Capture Baselines

Locate Item
  1. Click the triangle next to the item you want to capture a baseline for.
  2. In the context sensitive drop-down menu, click Capture baselines.

2. Capture Baselines

Capture Baselines
  • Click Capture.

3. View Baselines

View Baselines
  • View confirmation message and updated Baseline Start and Baseline End dates.