PowerSteeringPowerSteering User GuidesEnd User Guide Working with CostsHow do I change the display on the actual costs page?

How do I change the display on the actual costs page?

On the actual costs page, a user can view actual costs for the selected work only or display costs for the work and all of its descendants. This article describes how to change the display on the actual costs page.

1. Click Actual Costs

Click Actual Costs
  1. Click the Project button on the Icon Bar.
  2. Click Costs to expand the menu, then click Actual Costs.

Note: Clicking the Project button on the Icon Bar will take you directly to the summary page of the last work you visited.

2. Click Show All Levels

  • Click Show all levels.

3. View Actual Costs

  • View actual costs for the project and all descendants.

0 Comments

Add your comment

E-Mail me when someone replies to this comment