On the estimated costs page, a user can view estimated costs for the selected work only or display costs for the work and all of its descendants. This article describes how to change the display on the estimated costs page.

1. Click Estimated Costs

Click Estimated Costs
  1. Click the Project button on the Icon Bar.
  2. Click Costs to expand the menu, then click Estimated Costs.

Note: Clicking the Project button on the Icon Bar will take you directly to the summary page of the last work you visited.

2. Click Show All Levels

  • Click Show all levels.

3. View Estimated Costs

  • View estimated costs for the project and all descendants.