ESG - New Functionality

Click the Project Central Button

Click the Project Central Button

Select Project Planning.

The Project Planning window

Enter Scheduled End Date

  1. Click a field in the Scheduled End column.
  2. Select the desired month, date and year to populate the Scheduled End date.  

Note: Use the arrows at the top of the calendar box to change months. Click the year at the bottom to change years.  

View Scheduled End Date

The Constraint End for Plan is extended to 6/28 and it's Duration is extended to 8d

The Scheduled Start and Constraint Start date for Execute update to 7/01 since 6/28 is a Friday

The Scheduled Duration for Execute compresses to 2d in order to preserve the previously Scheduled End date of 7/02