How does the Must Start On (MSO) constraint affect my project schedule?
Project Central uses constraint type rules, along with work durations and dependencies, to determine the scheduled start and scheduled end dates of work items in your plan. With MSO selected as the constraint type, the Scheduled Start date will be the date entered regardless of other scheduling factors such as dependencies. This article describes how the MSO constraint works.