How does the As Late As Possible (ALAP) constraint affect my project schedule?
Project Central uses constraint type rules, along with work durations and dependencies, to determine the scheduled start and scheduled end dates of work items in your plan. With ALAP selected as the constraint type, the start and end dates of items will be as late as possible, given the current date, duration, and dependencies. This article describes how the ALAP constraint works.