In Project Central you have the ability to view dates by day, week, month and quarter. You can save these date settings as part of your layout. This article describes how to change the date display in Project Central.

1. The Date Range Slider

The date range slider allows you to change the date range to a daily, weekly, monthly or quarterly display. Looking at the image above the numbers represent each time frame:

1: The first position of the slider, represented with the number one, is the correct position for a daily view of the Project Central Gantt chart.

2: The second position of the slider, represented with the number two, is the correct position for a weekly view of the Project Central Gantt chart.

3: The third position of the slider, represented with the number three, is the correct position for a monthly view of the Project Central Gantt chart.

4: The fourth position of the slider, represented with the number four, is the correct position for a quarterly view of the Project Central Gantt chart.

1.1. Daily Display

The above image shows how the Project Central Gantt chart appears in the daily date range display.

1.2. Weekly Display

The above image shows how the Project Central Gantt chart appears in the weekly date range display.

1.3. Monthly Display

The above image shows how the Project Central Gantt chart appears in the monthly date range display.

1.4. Quarterly Display

The above image shows how the Project Central Gantt chart appears in the quarterly date range display.

2. Enlarge Date Range

The Enlarge Date Range button adds additional date periods onto the end of your Gantt chart schedule.

3. Jump to Today

The Jump to today button forces PowerSteering to display the time period that corresponds to today's date.