PowerSteeringPowerSteering User GuidesEnd User Guide Managing WorkHow do I capture a baseline for my entire project?

How do I capture a baseline for my entire project?

A baseline is generally captured at the beginning of a project and is a snapshot of forecasted information such as planned dates and costs. Baselines help to measure actual performance versus planned performance, and can also be useful when planning future projects. This article describes how to capture a baseline.

1. Click Capture Baselines

Click Capture Baselines
  1. On the Icon Bar, click the Project button.
  2. Click More to expand the menu, then click Capture Baselines.

2. Click OK

Click OK
  • Click Ok.

3. Click OK

Click OK
  • Click Ok.

0 Comments

Add your comment

E-Mail me when someone replies to this comment